Tuban Refinery Project Progress Reaches 49% as FEED Nears Completion
PT Pertamina Rosneft Pengolahan and Petrokimia (PRPP), as the Tuban GRR project executor, reported the Front-End Engineering Design (FEED) on March 31 reached 90.99 percent. This design process runs faster than the target set by 87.84 percent. This process is expected to produce extra complex design designs to process crude oil into international standard fuel oil and petrochemical products.
The Company has been running FEED activities since March 16 in collaboration with Tecnicas Reunidas SA (TRSA), a Spain-based company engaged in Engineering, Procurement, and Construction (EPC) as an engineering design contractor. In the FEED stage, TRSA develops the design of open-art units, off-site facilities and utilities, monitoring, and overall design integration, including design data from licensor technology.
"The achievement is on the back of collaboration between PRPP Engineering Team and TRSA as a solid FEED contractor to ensure the FEED completion," Eriyadi, PRPP Development Director, said on Tuesday.