West Betara Project Completion Could Maintain Jabung Block Production

PetroChina International Jabung Ltd has completed the West Betara Non-Associated Gas (WB-NAG) Compression and Condensate Pumping System Project to maintain the gas production of Jabung Block. Operational since August 18, 2021, the project focuses on gas supply distribution from the West Betara (WB) and South Betara (SB) fields. Meanwhile, the commissioning and start-up stages of the WB-NAG Project had been completed on August 22, 2021.
However, the project started quite a bit late from the initial target of July 12, 2021, due to the public activity restrictions (PPKM) set by the government. "The facility completion of the WB-NAG Compression and Condensate Pumping System is important to maintain gas source from WB and SB field, also as a follow up on PCJL program that has been approved to Put on Production of four gas wells from the Baturaja Formation with a total target rate of 7.5 MMscfd," General Manager of PetroChina International Jabung, Wang Qilin, revealed in a written statement on Friday (8/27).