PLN to Spend Rp 5 Trillion for Asahan 3 Hydropower Plant

Summary

PT Perusahaan Listrik Negara (PLN) will build the Asahan 3 Hydropower Plant (PLTA Asahan 3) with a total capacity of 2x87 megawatts (MW) in North Sumatra. The state-owned electricity company expects it to operate in March 2024, with an investment of Rp 5 trillion.

PLN Director of Mega Projects and Renewables, M. Ikhsan Asaad, revealed that the project would be one of PLN's Green transformation projects to gradually increase the renewable portion in the country’s energy mix following the increasingly high electricity demand. Ikhsan ensured that the Asahan 3 hydropower power project would continue despite the pandemic by maintaining the health protocol compliance.

"In February 2021, we managed to divert the flow of Asahan River to the diversion channel so that the intake weir construction could start immediately," Ikhsan explained in a written statement, Tuesday (15/6). While on the downstream side, the excavation work for the underground powerhouse, which began in June 2020, has been completed in May 2021. The powerhouse is the primary building where turbines and generators operate underground at a depth of approximately 150 meters.

Register now and get free access.

If you want to get free access to our Daily Insights and Weekly Digest, please click "Sign up" button below. If you already have an account, please login.

What do subscribers receive?

As a subscriber, you'll receive daily insights, weekly business digests, and quarterly industrial reports.

What kind of pieces will i get?

In-depth reports on assumption and impact analysis, as well as update and trends mapping, written by our credible and experienced analysts.

And, there is something else…

Register now and get free access, click here to register. Feel free to contact us with any additional questions you have.